Here's a look at the people and equipment at the Eppley site daily, as well as materials needed for the job.
900 safety driving tests given to equipment operators
150 -foot-high pile of new runway materials, if stacked onto a football field
80 Hawkins Construction workers
55 subcontractor workers
45 dump trucks
34 tons of grass seed
14 miles of electrical conduit
8 bulldozers
7 backhoes
6 off-road haul trucks
4 miles of new storm pipe installed
3 paving machines, one bought for this job for $1 million
3 water trucks to reduce dust on working runways
2 power broomers to keep working runways clear of debris